Testing & Commissioning
Network Integration Verification
Confirming the right device clears the fault, so a spur fault does not take out an entire feeder.
Protection coordination means the device closest to a fault operates first, disconnecting the smallest possible section of network. Get it wrong and a fault on a small spur trips the main incomer instead, taking out every customer on the feeder rather than a handful.
This is a separate commissioning step from functional testing, and it is the one most often skipped. A recloser can pass every test on its own and still be badly coordinated with what sits upstream of it.
What verification covers
- Review of upstream and downstream protection settings
- Coordination margin assessment across the fault range
- Grading verification between devices in series
- Confirmation of discrimination for both phase and earth faults
- Adjustment of settings where grading is inadequate
- Record of the coordinated scheme as commissioned
What matters in practice
-
Grading needs margin
Two devices that operate at almost the same time are not coordinated. Adequate margin between them is what produces reliable discrimination.
-
Both phase and earth
A scheme that grades correctly for phase faults can still be badly coordinated for earth faults. Both get checked.
-
Across the fault range
Coordination that holds at maximum fault level can fail at minimum. The margin is assessed across the range, not at one point.
-
Documented for the next change
The coordinated scheme is recorded, so the next person adding a device to this feeder can grade against it.